IIT barn

IIT barn
spring 2011 prototype

Wednesday, October 19, 2011

Permit meeting

10/12
We went to the Kendall County Permit office and discussed our building with them to get a better understanding of what will be needed to get the permit for our building. We found out that our building's lowest floor needs to be at least one foot above the flood plane elevation. Both of our schemes work so we don't need to move our building on the site for our scheme in order to fit the code. We also got names of places to get concrete and found out that the permit office will take 5-8 business days to process our drawings.

We are moving along to get the permit drawings done so we can build as soon as possible.

No comments:

Post a Comment