Concrete pours

4/23 poured the slab
5/3 poured the walls
In the past two weeks, we've poured both the slab and walls. We passed both inspections and learned alot both putting up the supports to the formwork and the pour itself. The concrete was faster than we all expected, and the limited time frame to finish the pour was difficult a we were learning as we did it.

















We also moved all of our walls to the site. We had one company move all of our wood, plus the stuff we bought in one big shipment, rather than separate.